As part of a four-phase project, an inspection was
conducted of the existing 671-slip marina to assess existing conditions
and estimate remaining service life for the dock system. Work included
inspection of existing dock system, guide piles, and utilities. Evaluations
of the dock systems were provided to guide the planning process for
the rehabilitation of the marina facilities. Marina layout plans and
conceptual costs estimates were developed for three primary rehabilitation
alternatives.